Agric. Econ. - Czech, 2014, 60(11):517-523 | DOI: 10.17221/51/2014-AGRICECON

Discussion with the paper 'Project costs planning in the conditions of uncertainty' by H. ŠtikováOriginal Paper

Igor KREJČÍ, Milan HOUŠKA
Department of Systems Engineering, Faculty of Economics and Management, Czech University of Life Sciences Prague, Prague, Czech Republic

In the paper, there is analysed one particular approach to the modelling uncertainty in the project management through an original version of the fuzzy CPM (Critical Path Method). First there is shown the relevance of using the fuzzy CPM in agriculture and the related branches and present the basics of the methods used. Then, there are described the imperfections of the work which is discussed and the impacts of the previously-published approach when applied in project management practice are emphasised. In the original paper, the author uses only the discrete fuzzy numbers for activity time durations which could be considered inappropriate for the time scheduling in project management. Consecutively, the direct application of the extension principle on the comparison of continuous durations could lead to the situation when both numbers can be greater than the second one with possibility equal to one. Moreover, the simple transformation of durations to the costs by linear equations with a positive slope does not respect the current project management theory and practice. Finally, the missing comparison of project fuzzy costs among individual variants of the project is calculated.

Keywords: project management, fuzzy critical path method, project costs, project schedule

Published: November 30, 2014  Show citation

ACS AIP APA ASA Harvard Chicago Chicago Notes IEEE ISO690 MLA NLM Turabian Vancouver
KREJČÍ I, HOUŠKA M. Discussion with the paper 'Project costs planning in the conditions of uncertainty' by H. Štiková. Agric. Econ. - Czech. 2014;60(11):517-523. doi: 10.17221/51/2014-AGRICECON.
Download citation

References

  1. Boháčková I. (2014): Some notes to income disparity problems of agriculture. Agris on-line Papers in Economics and Informatics, 5: 25-34.
  2. Bregman R.L. (2009): Preemptive expediting to improve project due date performance. Journal of the Operational Research Society, 60: 120-129. Go to original source...
  3. Carrosio G. (2013): Energy production from biogas in the Italian countryside: Policies and organizational models. Energy Policy, 63: 3-9. Go to original source...
  4. Colliver D.G., Brook R.C., Peart R.M. (1978): Optimal management procedures for solar grain drying. Winter Meeting of the American Society of Agricultural Engineers, 18 December 1978, Chicago, 12: 14.
  5. Cooke-Yarborough R.E. (1964): Critical path planning and scheduling: An introduction and example. Review of Marketing and Agricultural Economics, 32: 36-48.
  6. Coupland G.A., Halyk R.M. (1969): Critical Path Scheduling of Forage Harvesting Systems in Quebec. Winter Meeting of the American Society of Agricultural Engineers, 18 December 1978, Chicago, 3: 11.
  7. Chanas S., Dubois D., Zieliński P. (2002): On the sure criticality of tasks in activity networks with imprecise durations, IEEE Transactions on Systems, Man, and Cybernetics - Part B: Cybernetics, 32: 393-407. Go to original source... Go to PubMed...
  8. Dubois D., Fargier H., Fortemps P. (2003): Fuzzy scheduling: Modelling flexible constraints vs. Coping with incomplete knowledge. European Journal of Operational Research, 147: 231-252. Go to original source...
  9. Dubois D., Prade H. (eds.) (2000): Fundamentals of fuzzy sets. 1st ed. Kluwer Academic Publishers, Norwell; ISBN: 0-7923-7732-X. Go to original source...
  10. Fortin J., Zieliński P., Dubois D. (2010): Criticality analysis of activity networks under interval uncertainty. Journal of Scheduling, 13: 609-627. Go to original source...
  11. Gagnon M. (2002): COA Modeling with Fuzzy Information, International, [online]. Command and Control Research and Technology Symposium. Available at <www.dodccrp.org/events/7th_ICCRTS/Tracks/pdf/145.PDF> (accessed 15. 7. 2013).
  12. Han T.C., Chung C.C., Liang G.S. (2006): Application of fuzzy critical path method to airport's cargo ground operation system. Journal of Marine Science and Technology, 14: 139-146. Go to original source...
  13. Kelley J.E., Walker M.R. (1959): Critical-path planning and scheduling. Proceedings of the Eastern Joint Computer Conference, Boston, pp. 160-173. Go to original source...
  14. Khambalkar V.P., Kankal U.S., Gangde C.N. (2013): Rural village level energy planning and management options: An assessment of biomass energy. World Applied Sciences Journal, 25: 1087-1099.
  15. Lewis J.P. (2005): Project Planning, Scheduling & Control. McGraw Hill. ISBN 978-0-07-146037-8.
  16. Malcolm D.G., Roseboom J.H., Clark C.E., Fazar W. (1959): Application of a technique for research and development program evaluation. Operations Research, 7: 646-669. Go to original source...
  17. Mareš M. (1997): Weak arithmetic of fuzzy numbers. Fuzzy Sets and Systems, 91: 143-154. Go to original source...
  18. Mareš M. (2000): Metoda kritické cesty s vágními délkami činností. (Critical path method with vague lengths of activities.) Acta Oeconomica Pragensia, 8: 48-59.
  19. Mareš M. (2002): Algebraické vlastnosti fuzzy veličin. (Algebraic properties of fuzzy quantities.) In: ROBUST´2002, pp. 224-239; ISBN 80-7015-900-6.
  20. Monjezi N., Sheikhdavoodi M.J., Basirzadeh H., Zakidizaji H. (2012): Analysis and evaluation of mechanized greenhouse construction project using CPM methods. Research Journal of Applied Sciences, Engineering and Technology, 4: 3267-3273.
  21. Sharafi M., Jolai F. Iranmanesh H., Hatefi S. M. (2008): A model for project scheduling with fuzzy precedence. Australian Journal of Basic and Applied Science, 4: 1356-1361.
  22. Sireesha V., Shankar R.A. (2010): New approach to find total float time and critical path in a fuzzy project network. International Journal of Engineering Science and Technology, 2: 600-609.
  23. Soltani A., Haji R. (2007): A project scheduling method based on fuzzy theory. Journal of Industrial and Systems Engineering, 1: 70-80.
  24. Štiková H. (2012): Project costs planning in the conditions of uncertainty. Agricultural Economics - Czech, 58: 71-84. Go to original source...
  25. Šubrt T. (2004): Multiple criteria network models for project management. Agricultural Economics - Czech, 50: 71-75. Go to original source...
  26. Torrellas M., Antón A., Montero J.I. (2013): An environmental impact calculator for greenhouse production systems. Journal of Environmental Management, 118: 186-195. Go to original source... Go to PubMed...
  27. Wang X., Kerre E.E. (2001): Reasonable properties for the ordering of fuzzy quantities (I). Fuzzy Sets and Systems, 118: 375-385. Go to original source...
  28. Zadeh L.A. (1965): Fuzzy Sets. Information and Control, 8: 338-353. Go to original source...
  29. Zang H.G., Liu D. (2006): Fuzzy Modeling and Fuzzy Control. Birhäuser, Boston; ISBN 0-8176-4491-1.

This is an open access article distributed under the terms of the Creative Commons Attribution-NonCommercial 4.0 International (CC BY NC 4.0), which permits non-comercial use, distribution, and reproduction in any medium, provided the original publication is properly cited. No use, distribution or reproduction is permitted which does not comply with these terms.